920
|
JOINT RESOLUTIONS.
house be and said committee is hereby author-
ized and requested, in drawing under said act
upon the amount appropriated for said building,
to set apart and reserve a sum sufficient to pay
said workmen their several sworn and undis-
puted claims as ascertained by said joint com-
mittee, and also to set apart and reserve out of
the amount so appropriated for said building a
sum sufficient to pay all other unpaid bills and
claims of material men or sub-contractors for
work done upon or material provided for said
building, and which have been or may hereafter
|
|
|
Conditions to
be enforced.
|
be exhibited or made known to said building
committee; and said building committee is re-
quested and authorized not to accept said build-
ing from the contractor or contractors for the
same unless he or they shall first agree to the
reservation by said committee, out of the amount
of said appropriation otherwise coming to such
contractor or contractors, of a sum sufficient to
meet all of such unpaid claims as made known
to said committee when the building is other-
wise ready for acceptance.
And be it resolved, That said building com-
|
|
|
To inquire
into correct-
nees of claims.
|
mittee is hereby further authorized and re-
quested to inquire into the correctness of the
several claims so made known to them, and to
pay out of the amount so reserved, and to charge
to the account of said contractor or contractors
such of said claims as are undisputed as to their
amount, and that whether the work and labor
(in claims for work and labor) were done for the
contractor or contractors, or for sub-contractors,
|
|
|
Pay claims.
|
on said building; and also to pay out of the
amount so reserved, and to charge to the account
of said contractor or contractors, all other undis-
puted claims on account of said building re-
served for by them as aforesaid; and as to all dis-
puted claims said committee is authorized and
requested to refuse to pay over the amount so
reserved for them, either to the claimants or to
the contractor or contractors, until they have re-
spectively litigated the matters of dispute be-
tween them and had the same adjudicated by a
court of competent jurisdiction, in which event
said building committee shall pay over the
|
|
|
|
|
|
|
|