(2) Change the scope of a project in the
construction program or development and
evaluation program meeting the definition
of "major project" under § 2-103.1 of the
Transportation Article, which will result in
an increase of more than 10% or $1.0
million, whichever is greater, in the total
project cost as reviewed by the General
Assembly during a prior session, the
department shall prepare a report to notify
the budget committees of the proposed
changes. For each change, the report shall
identify the project title, justification for
adding the new project or modifying the
scope of the existing project, current year
funding levels and the total project cost
estimate as approved by the General
Assembly during the prior session compared
with the proposed current year funding and
total project cost estimate resulting from the
project addition or change in scope.
Notification of changes in scope shall be made
to the General Assembly concurrent with
the submission of the draft and final CTP.
Notification of new construction project
additions, as outlined in paragraph (1)
above, shall be made to the General
Assembly prior to the expenditure of funds
or the submission of any contract for
approval to the Board of Public Works.
- 409 -
PARRIS N. GLENDENING, Governor
Ch. 7
SECRETARY'S OFFICE
29.01.01.01 Executive Direction
Special Fund Appropriation.............................
Funds are appropriated in the Department of
General Services budget to pay for services
provided by this program. Authorization is
hereby granted to use these receipts as
special funds for operating expenses in this
program.
29.01.01.02 Operating Grants-In-Aid
14,354,94 9
13,130,218
|