1678 LAWS OF MARYLAND Ch. 600
(III) Individual water supply systems may
be installed and used during an interim period, pending the
availability of a programmed community water supply system.
In Harford County, within the areas outlined in the county
plan to receive a community water supply system within ten
years, any new subdivisions approved after June 1, 1972,
must have a county-approved water distribution system as a
prerequisite for the issuance of building and zoning
permits.
(IV) Individual water supply systems may
be installed and used for an indefinite period. In Harford
County, within the areas outlined in the county plan to
receive a community water supply system within ten years,
any new subdivisions approved after June 1, 1972, must have
a county—approved water distribution system as a
prerequisite for the issuance of building and zoning
permits.
(V) Community sewerage systems must be
provided;
(VI) Multiuse sewerage systems may be
installed;
(VII) Individual sewerage systems may be
installed and used during an interim period, pending
availability of a programmed community sewerage system. In
Harford County, within the areas outlined in the county plan
to receive community sewerage system within ten years, any
new subdivisions approved after June 1, 1972, must have a
county—approved sewerage collection system as a prerequisite
for the issuance of building and zoning permits. In
Montgomery and Prince George's counties the comprehensive
water and sewerage plan may permit individual sewerage
systems to be installed and used during an interim period,
pending the availability of sewerage transmission and
treatment capacity necessary to provide adequate community
sewerage service, for properties which otherwise would be in
an area where community sewerage systems are required but
where access to such community systems is prohibited by an
order of the Department, Montgomery County, Prince George's
County, or the Washington Suburban Sanitary Commission.
(VIII) Individual sewerage systems may be
installed and used for an indefinite period. In Harford
County, within the areas outlined in the county plan to
receive community sewerage system within ten years, any new
subdivisions approved after June 1, 1972, must have a
county—approved sewerage collection system as a prerequisite
for the issuance of building and zoning permits.
(IX) Community solid waste disposal
systems must be provided.
|