REPORT OF THE COMPTROLLER OF THE TREASURY 83
STATEMENT A—13—Continued
|
Character of Bonded Debt
|
Amount of
Bonds Issued
and
Outstanding
|
Maturity
|
Purpose of Bond Issue
|
|
Maryland School for the Blind Loan of
|
|
|
|
|
1949, 1 1/4 %, per Chapter 6 of the
|
|
|
|
|
Acts of 1949, Extraordinary Session
|
|
|
|
|
amended by Chapter 48 of the Acts
|
|
|
|
|
of 1950
|
|
|
|
|
Series "M "...............
|
$32,000.00
|
Feb. 1, 1965
|
Construction and
|
|
|
|
|
Equipment
|
|
Total.......
|
$32,000 00
|
|
|
|
General Construction Loan of 1950,
|
|
|
|
|
1 3/4 %, per Chapter 109 of the Acts of
|
|
|
|
|
1950
|
|
|
|
|
Series "L"......................
|
$343,000.00
|
Mar. 1, 1965
|
Land, Construction,
|
|
Senes "M"......................
|
355,000.00
|
Mar. 1, 1966
|
Equipment and
|
|
|
|
|
Deferred Maintenance
|
|
Total.........
|
$698,000.00
|
|
|
|
Mental Hospital Construction Loan of
|
|
|
|
|
1950, 1 3/4 % per Chapter 48 of the
|
|
|
|
|
Arts of 1950
|
|
|
|
|
Series "K"........
|
$232,000.00
|
Oct. 1, 1964
|
Erecting, Equipping,
|
|
Series "L". .....................
|
237,000.00
|
Oct. 1, 1965
|
Improving and Kepair-
|
|
Series "M"......................
|
243,000.00
|
Oct. 1, 1966
|
ing Buildings at Spnng
|
|
|
|
|
Grove State Hospital
|
|
Total...............
|
$712,000.00
|
|
and Rosewood State
|
|
|
|
|
Training School
|
|
General Construction Loan of 1951, per
|
|
|
|
|
Chapter 412 of the Acts of 1951
|
|
|
|
|
Series "K" 1 1/2%
|
$249,000.00
|
Oct. 1, 1964
|
|
|
Series "L" 1 1/2%....
|
254,000.00
|
Oct. 1, 1965
|
Land, Construction,
|
|
Senes "M" 1 1/2%.......
|
260,000.00
|
Oct. 1, 1966
|
Equipment and
|
|
Series "W" 13/4%
|
1,303,000.00
|
Nov. 1, 1964
|
Deferred Maintenance
|
|
Series "X" 1 3/4 %...
|
1,329,000.00
|
Nov. 1, 1965
|
|
|
Senes "Y" 13/4%
|
1,356,000 00
|
Nov. 1, 1966
|
|
|
Series "Z" 13/4%....
|
1,883,000.00
|
Nov. 1, 1967
|
|
|
Total.......
|
$6,134,000.00
|
|
|
|
Civil Defense Loan of 1951, 13/4% per
|
|
|
|
|
Chapter 413 of the Acts of 1951
|
|
|
|
|
Series " J".........
Series "K".................
|
$81,000.00
83,000.00
|
Nov. 1, 1964
Nov. 1, 1965
|
Equipment, Supplies, and
building and operating
|
|
Senes "L"...
|
85,000.00
|
Nov. l, 1966
|
costs in connection
|
|
Senes "M"....
|
87,000.00
|
Nov 1, 1967
|
with Civil Defense
|
|
Total...............
|
$336,000.00
|
|
|
|
Johns Hopkins University Loan of 1951,
|
|
|
|
|
13/4%, per Chapter 414 of the Acts of
|
|
|
|
|
1951
|
|
|
|
|
Series "J"... ..............
Senes "K"...... .......
|
$122,000.00
125,000.00
|
Nov. 1, 1964
Nov 1, 1965
|
Erecting and Equipping
a new building for the
|
|
Senes "L".... ...........
|
127,000.00
|
Nov. 1, 1966
|
School of Engineering
|
|
Series "M"......................
|
130,000.00
|
Nov. 1, 1967
|
|
|
Total...............
|
$504,000.00
|
|
|
|
St. Mary's Seminary Junior College
|
|
|
|
|
Loan of 1951, 13/4%, per Chapter 626
|
|
|
|
|
of the Acts of 1951
|
|
|
|
|
Series "I".....................
|
$ 40,000.00
|
Dec. 1, 1964
|
|
|
Senes " J"......................
|
41,000.00
|
Dec. 1, 1965
|
Erecting and Equipping
|
|
Senes "K"......................
|
42,000.00
|
Dec. 1, 1966
|
new Building(s)
|
|
Series "L"................... ..
|
43,000.00
|
Dec. 1, 1967
|
|
|
Senes "M"......................
|
46,000.00
|
Dec. 1, 1968
|
|
|
Total... .
|
% 212,000.00
|
|
|
|
 |