REPORT OF THE COMPTROLLER OF THE TREASURY 73
STATEMENT A—13—Continued
Character of Loan
|
Amount of
Loan
|
Maturity
|
Purpose of Loan
|
General Construction Loan of 1950,
|
|
|
|
1 1/4%, per Chapter 109 of the Acts of
|
|
|
|
1950
|
|
|
|
Series "G"
|
$ 296,000 00
|
Mar 1, 1960
|
|
Series "H"
|
305,000 00
|
Mar 1, 1961
|
Land, Construction,
|
Series "I"
|
314,000 00
|
Mar. 1, 1962
|
Equipment and
|
Series "J"
|
323,000 00
|
Mar. 1, 1963
|
Deferred Maintenance
|
Series "K"
|
333,000.00
|
Mar 1, 1964
|
|
Series "L"
|
343,000 00
|
Mar 1, 1965
|
|
Senes "M"
|
355,000 00
|
Mar 1, 1966
|
|
Total
|
$2,269,000 00
|
|
|
Mental Hospital Construction Loan of
|
|
|
|
1950, 1 1/2%, per Chapter 48 of the
|
|
|
|
Acts of 1950
|
|
|
|
Senes "F"
|
$ 211,000 00
|
Oct 1, 1959
|
|
Series "G"
|
215,000 00
|
Oct 1, 1960
|
Erecting, Equipping,
|
Senes "H"
|
219,00000
|
Oct 1, 1961
|
Improving and
|
Senes "I"
|
223,000 00
|
Oct 1, 1962
|
Repairing Buildings
|
Series "J"
|
228,000 00
|
Oct 1, 1963
|
at Spring Grove
|
Senes "K"
|
232,000 00
|
Oct 1, 1964
|
State Hospital and
|
Series "L"
|
237,000 00
|
Oct. 1, 1965
|
Rosewood State
|
Series "M"
|
243,000 00
|
Oct 1, 1966
|
Training School
|
Total
|
$1,808,000.00
|
|
|
General Construction Loan of 1951,
|
|
|
|
per Chapter 412 of the Acts of 1951
|
|
|
|
Sene3"F" 1 1/2%
|
$ 226,000 00
|
Oct 1, 1959
|
|
Series "G" 1 1/2%
|
230,000.00
|
Oct. 1, 1960
|
|
Series "H" 1 1/2%
|
235,000 00
|
Oct 1, 1961
|
|
Series "I" 1 1/2%
Senes "J" 1 1/2%
|
239,000.00
244,000 00
|
Oct 1, 1962
Oct 1, 1963
|
Land, Construction,
|
Senes "K" 1 1/2%
|
249,000.00
|
Oct. 1, 1964
|
Equipment and
|
Series "L" 1 1/2%
|
254,000.00
|
Oct. 1, 1965
|
Deferred
|
Series "M" 1 1/2%
|
260,000.00
|
Oct 1, 1966
|
Maintenance
|
Senes "R" 1 1/2%
|
1,180,000.00
|
Nov. 1, 1959
|
|
Senes "S" 1 1/2%
|
1,204,000.00
|
Nov. 1, 1960
|
|
Series "T" 1 1/2%
|
1,228,000 00
|
Nov. 1, 1961
|
|
Senes "U" 1 1/2%
|
1,252,000.00
|
Nov. 1, 1962
|
|
Senes "V" 1 1/2%
|
1,277,000.00
|
Nov. 1, 1963
|
|
Series "W" 1 1/2%
|
1,303,000 00
|
Nov. 1, 1964
|
|
Senes "X" 1 1/2%
|
1,329,000.00
|
Nov. 1, 1965
|
|
Senes "Y" 1 1/2%
|
1,356,000.00
|
Nov. 1, 1966
|
|
Senes "Z" 1 1/2%
|
1,383,000.00
|
Nov. 1, 1967
|
|
Total
|
$13,449,000.00
|
|
|
Civil Defense Loan of 1951, 1 3/4%, per
|
|
|
|
Chapter 413 of the Acts of 1951
|
|
|
|
Series "E"
|
$74,000.00
|
Nov. 1, 1959
|
|
Series "F"
|
75,000 00
|
Nov. 1, 1960
|
|
Senes "G"
|
77,000.00
|
Nov. 1, 1961
|
Equipment, supplies,
|
Senea "H"
|
78,000.00
|
Nov. 1, 1962
|
and building and
|
Senes "I"
|
80,000.00
|
Nov. 1, 1963
|
operating costs in
|
Series "J"
|
81,000.00
|
Nov 1, 1964
|
connection with
|
Senes "K"
|
83,000.00
|
Nov. 1, 1965
|
Civil Defense
|
Senes "L"
|
85,000.00
|
Nov 1, 1966
|
|
Series "M"
|
87,000.00
|
Nov 1, 1967
|
|
Total
|
$ 720,000.00
|
|
|
|