10 REPORT OF THE COMPTROLLER OF THE TREASURY
Pasteurization Plant in the amount of $32,716.00 to be erected
out of the total allotment for the Hospital.
Eastern Shore State Hospital —
|
|
|
Utilities: Laundry..................................
|
... $20,000.
|
|
Pasteurizing, etc...................
|
... 17,000.
|
|
Farm Buildings (2)...............
|
1,200.
|
|
Cannery.................................
|
5,000.
|
|
Electric Plant.......................
|
... 35,000.
|
|
Bath Lockers.........................
|
800. $79,000.
|
|
Quarters for Employees........................
|
.................... 40,000.
|
$119,000.00
|
Rosewood State Training School —
|
|
|
Utilities: Tunnel..............................
|
... $164,000.
|
|
Power Plant......................
|
... 66,000.
|
|
Power Equipment.................
|
... 50,000.
|
|
Roads.....................................
|
... 25,000.
|
|
Lighting.................................
|
5,000. $310,000.
|
|
Quarters for Employees:
|
|
|
Remodeling 2 Buildings.......
|
.................... 180,000.
|
|
Buildings for Patients:
|
|
|
2 Dormitories........................
|
. $237,000.
|
|
Remodeling 4 Dormitories...
|
.. 360,000. 597,000.
|
1,087,000.00
|
Guttering, spouting, and replacement of roof slates at a cost
of $10,000.00 to come from total allotment to the School.
Spring Grove State Hospital :
|
|
|
Utilities: Power Plant..............................
|
$28,000.
|
|
Dairy........................................
|
20,000.
|
|
Laundry....................................
|
33,000.
|
|
Center Kitchen........................
|
22,000.
|
$103,000.
|
Quarters for Employees:
|
|
|
1/4 of Employees' Village.....
|
$25,000.
|
|
Medical Quarters....................
|
54,000.
|
$79,000.
|
Building for Patients:
|
|
|
Female Admitting Building
|
|
220,000.
|
Criminal Division:
|
|
|
Utilities.....................................
|
$88,000.
|
|
Quarters for employees..........
|
35,000.
|
|
Buildings for patients.............
|
706,000.
|
829,000. 1,231,000.00
|
Repairs to Roads at a cost of $16,780.00 paid for from total
allotment to Hospital.
Springfield State Hospital-
|
|
Utilities: Water Supply...................
|
....... $131,000.
|
Sewage Disposal...............
|
....... 61,000.
|
Hot Water Mains.............
|
....... 20,000.
|
Pasteurization Plant.........
|
8,000.
|
Stock Barn.......................
|
....... 20,000.
|
Electric Generator...........
|
....... 30,000.
|
Fire Escapes.....................
|
....... 8,000. $278,000.
|
|
|